This open house was active from June 18 - July 5, 2021. Information on this website may no longer be current. Email us for more information.
These dates are estimates and subject to change. Check www.wc-roads.com for current traffic impacts.
-
Online construction kickoff
June 18-July 5You are here
-
Begin construction
July 5, 2021 -
Phase 1 road closure
Sept. 1, 2021-Jan. 31, 2022Century Boulevard closed between Tualatin Valley Highway and Goodwill entrance. Detour
-
Phase 2 road closure
Dec. 17, 2021-Jan. 31, 2022Century Boulevard closed at Alexander Street and between Tualatin Valley Highway and Goodwill entrance. Detour
-
Phase 3 road closure
June 8-July 8, 2022Century Boulevard closed between Tualatin Valley Highway and Fred Meyer driveway. Detour
-
End of construction
Oct. 1, 2022